Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, November 28, 2023 at 7:12 AM

Select by Ship Name: 

Select by Ship Hull: 

 

JOHN PAUL JONES (DDG 53)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 10 EDSRA8   06/23/2010 - 03/04/2011 3 / 60 (b)   0 / 0 (f) 07/16/2008 Complete
FY 12 ESRA   09/12/2012 - 09/18/2013 3 / 18 (b)   11 / 36 (f) NA Complete
FY 17 SRA3-2   09/25/2017 - 10/12/2018 2 / 27 (b)   4 / 21 (f) 01/08/2013 Complete
  FY 23 DSRA3   10/31/2022 - 05/08/2024 3 / 60 (b)   7 / 29 (f) NA Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
JOHN PAUL JONES (DDG 53) 21313-231
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: EVERETT PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3761
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: N/A
SURVEY DATES: -
SURVEY LOCATION:
DESIGN AGENT:
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 23 DSRA3
INSTALL DATES: 10/31/2022 - 05/08/2024
INSTALL LOCATION: EVER
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 0 / 0 0 / 0 0 / 0 0 / 0 0 / 0
SANITARY SPACE / FIXTURES: 0 / 0 0 / 0 0 / 0 0 / 0 0 / 0
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 3 / 60 0 / 0 0 / 0 0 / 0 3 / 60
SANITARY SPACE / FIXTURES: 7 / 29 0 / 0 0 / 0 0 / 0 7 / 29
OTHER PROJECT:
PROJECT NO(S):
REMARKS:
OTHER PROJ:
REMARKS: HRPR-S1356, 2-321-0-L IS INSTALLATION OF 4TH SHOWER IN CREW COMPLEX 3 WASH
ROOM/WATER CLOSET/SHOWER CALLED OUT IN SCD DDG 51-89646 BIWPY RLAR 89646/DDG53/1163875. AVAIL PUSHED TO AUG 2022.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
USS ARLEIGH BURKE (DDG 51) REV E DRAWINGS WILL BE USED FOR THIS INSTALLATION
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S
3-300-1-L (24)
3-310-2-L (18)
3-338-1-L (18)
 PT 3 (60)
HENL-S
3-300-2-L (5)
3-306-2-A (1)
3-325-1-L (6)
3-335-1-A (1)
3-338-3-A (1)
3-338-5-L (5)
 PT 6 (19)
HRPR-S1356
2-321-0-L (10)
 PT 1 (10)
MILESTONES SCHEDULED ACTUAL EVENTS
07/08/2021 07/03/2020 07/09/2020 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
08/06/2021 08/03/2020 08/17/2020 SHIP RESPOND TO ADVANCE PLANNING NOTICE
10/31/2022 10/31/2022 10/31/2022 START AVAILABILITY
10/31/2022 10/31/2022 10/31/2022 START PROJECT
05/08/2024 05/08/2024 Pending COMPLETE PROJECT
05/08/2024 05/08/2024 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 10/30/2023