Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Thursday, November 7, 2024 at 12:42 PM

Select by Ship Name: 

Select by Ship Hull: 

 

BOXER (LHD 4)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 10 DPMA6   10/14/2009 - 06/09/2010 1 / 133 (b)   4 / 27 (f) 03/14/2009 Complete
FY 12 PMA   01/11/2012 - 09/07/2012 1 / 165 (b)   4 / 33 (f) 10/14/2009 Complete
FY 14 PMA3-2   07/07/2014 - 03/24/2015 2 / 354 (b)   4 / 51 (f) 03/13/2012 Complete
FY 17 PMA3-3   11/28/2016 - 03/02/2018 1 / 216 (b)   4 / 35 (f) 03/13/2012 Complete
FY 20 DSRA3   06/15/2020 - 03/30/2022 7 / 518 (b)   15 / 92 (f) 04/18/2017 Complete
  FY 25 SRA4-1   04/14/2025 - 10/11/2026 4 / 476 (b)   12 / 92 (f) 11/03/2020 Active
FY 29 SRA4-2   03/12/2029 - 05/27/2030 4 / 460 (b)   10 / 73 (f) 06/03/2025 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
BOXER (LHD 4) 21808-253
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: SDGO PLANNING YARD: NNSY
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3795
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 20 DSRA3
SURVEY DATES: 06/15/2020 - 03/30/2022
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 25 SRA4-1
INSTALL DATES: 04/14/2025 - 10/11/2026
INSTALL LOCATION: SDGO
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 393 2 / 83 0 / 0 0 / 0 4 / 476
SANITARY SPACE / FIXTURES: 8 / 67 4 / 24 0 / 0 0 / 0 12 / 91
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 393 2 / 83 0 / 0 0 / 0 4 / 476
SANITARY SPACE / FIXTURES: 8 / 67 4 / 25 0 / 0 0 / 0 12 / 92
OTHER PROJECT:
PROJECT NO(S): BCPO-E0440, BENL-E0441, HCPO-E0448, HENL-E0449
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 21-LHD 4-01  - 640 - 8866598  REV -
ARRANGEMENT-SANITARY 21-LHD 4-03  - 644 - 8866599  REV -
VENTILATION-BERTHING 21-LHD 4-10  - 512 - 8866600  REV -
VENTILATION-SANITARY 21-LHD 4-12  - 512 - 8866601  REV -
PIPE-FLUSHING WATER 21-LHD 4-26  - 521 - 8866602  REV -
PIPE-PLUMBING DRAIN 21-LHD 4-27  - 528 - 8866603  REV -
PIPE - POTABLE 21-LHD 4-28  - 533 - 8866604  REV -
ELECTRICAL-BERTHING 21-LHD 4-30  - 331 - 8866605  REV -
ELECTRICAL-SANITARY 21-LHD 4-32  - 331 - 8866606  REV -
ELECTRICAL-POWER SYSTEM 21-LHD 4-39  - 321 - 8866607  REV -
VENTILATION-MFG DET 21-LHD 4-52  - 512 - 8866608  REV -
PROJECT NUMBERS(s) AND COMPARTMENTS
BCPO-S0440
2-41-01-L (74)
2-43-0-L (9)
 PT 2 (83)
BENL-S0441
2-33-0-L (249)
3-25-0-L (144)
 PT 2 (393)
HCPO-S0448
2-41-0-L (7)
2-41-1-L (7)
2-41-3-L (5)
2-42.5-1-L (6)
 PT 4 (25)
HENL-S0449
2-39-0-L (15)
2-39.5-0-L (16)
2-39.5-1-L (10)
2-39.5-2-A (1)
3-31-0-L (10)
3-31-2-L (9)
3-32-0-L (5)
3-33-3--A (1)
 PT 8 (67)
MILESTONES SCHEDULED ACTUAL EVENTS
06/15/2023 11/03/2020 11/03/2020 START SURVEY
07/14/2023 11/14/2020 11/14/2020 COMPLETE SURVEY
08/15/2023 12/14/2020 12/01/2020 SEND SURVEY REPORT TO PM
12/21/2023 10/10/2023 11/06/2023 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
01/19/2024 11/09/2023 11/07/2023 SHIP RESPOND TO ADVANCE PLANNING NOTICE
02/16/2024 02/16/2024 04/12/2024 SO SUBMIT DRAWINGS TO PM & PY
02/16/2024 02/16/2024 04/15/2024 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
10/16/2024 10/16/2024 Pending PROJECT MATERIAL PROCUREMENT FUNDED
01/13/2025 01/13/2025 Pending PROJECT INSTALLATION FUNDED
04/14/2025 04/14/2025 Pending START AVAILABILITY
04/14/2025 04/14/2025 Pending START PROJECT
10/11/2026 10/11/2026 Pending COMPLETE PROJECT
10/11/2026 10/11/2026 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 06/12/2024