S H I P H A B I T A B I L I T Y P R O J E C T D A T A
STETHEM (DDG 63) |
21825-243
ACTIVE PROJECT
|
TYCOM: SURFPAC |
HOMEPORT: SDGO |
PLANNING YARD: BATH |
|
POC: Steve Ferderer, CNSP N43 |
PHONE: 619-437-3761 |
|
ENGINEERING WORK SCOPE |
SURVEY AVAILABILITY: |
FY 20 EDSRA |
SURVEY DATES: |
10/01/2019 - 09/30/2021 |
SURVEY LOCATION: |
SDGO |
DESIGN AGENT: |
DELPHINUS |
|
INSTALLATION WORK SCOPE |
INSTALL AVAILABILITY: |
FY 24 SRA3-1 |
INSTALL DATES: |
04/08/2024 - 02/25/2025 |
INSTALL LOCATION: |
SDGO |
SHIPYARD: |
SRF JRMC |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
6 / 174 |
4 / 27 |
0 / 0 |
0 / 0 |
10 / 201 |
SANITARY SPACE / FIXTURES: |
11 / 44 |
5 / 17 |
0 / 0 |
0 / 0 |
16 / 61 |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
5 / 78 |
0 / 0 |
0 / 0 |
0 / 0 |
5 / 78 |
SANITARY SPACE / FIXTURES: |
8 / 25 |
0 / 0 |
0 / 0 |
0 / 0 |
8 / 25 |
|
OTHER PROJECT: |
|
PROJECT NO(S): |
BCPO-E0466, BENL-E0467, HCPO-E0468, HENL-E0469 |
REMARKS: |
|
|
|
HABITABILITY DRAWING NUMBERS |
DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
ARRANGEMENT-BERTHING |
20-DDG 63-01 A |
640 - 8866540 REV A |
ARRANGEMENT-SANITARY |
20-DDG 63-03 A |
644 - 8866541 REV A |
VENTILATION-BERTHING |
20-DDG 63-10 A |
512 - 8866542 REV A |
VENTILATION-SANITARY |
20-DDG 63-12 A |
512 - 8866543 REV A |
PIPE-SANITARY |
20-DDG 63-20 A |
505 - 8866544 REV A |
ELECTRICAL-BERTHING |
20-DDG 63-30 A |
331 - 8866545 REV A |
ELECTRICAL-SANITARY |
20-DDG 63-32 A |
331 - 8866546 REV A |
VENTILATION-MFG DET |
20-DDG 63-52 A |
512 - 8866547 REV A |
|
PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S0467
3-300-1-L (24)
3-310-2-L (18)
3-326-1-L (0)
3-338-1-L (18)
3-338-2-L (18)
PT 5 (78)
HENL-S0469
3-300-2-L (5)
3-306-2-A (1)
3-325-1-L (6)
3-335-1-A (1)
3-338-3-A (1)
3-338-4-A (1)
3-338-5-L (5)
3-338-6-L (5)
PT 8 (25)
|
|
MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
06/09/2022 |
03/03/2020 |
03/03/2020
|
START SURVEY |
07/08/2022 |
03/14/2020 |
03/18/2020
|
COMPLETE SURVEY |
08/09/2022 |
04/14/2020 |
03/31/2020
|
SEND SURVEY REPORT TO PM |
12/15/2022 |
11/10/2022 |
10/07/2022
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
01/13/2023 |
02/13/2023 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
02/13/2023 |
01/27/2023 |
02/03/2023
|
SO SUBMIT DRAWINGS TO PM & PY |
02/13/2023 |
01/27/2023 |
02/03/2023
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
10/11/2023 |
10/11/2023 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
01/08/2024 |
01/08/2024 |
Pending
|
PROJECT INSTALLATION FUNDED |
04/08/2024 |
04/08/2024 |
Pending
|
START AVAILABILITY |
04/08/2024 |
04/08/2024 |
Pending
|
START PROJECT |
02/25/2025 |
02/25/2025 |
Pending
|
COMPLETE PROJECT |
02/25/2025 |
02/25/2025 |
Pending
|
COMPLETE AVAILABILITY |
Project Record Last Updated: 06/09/2023 |
|