Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, September 10, 2024 at 8:39 AM

Select by Ship Name: 

Select by Ship Hull: 

 

HARPERS FERRY (LSD 49)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 11 EDPMA   07/13/2011 - 12/03/2012 4 / 123 (b)   4 / 28 (f) 09/28/2007 Complete
FY 17 PMA3-2   12/05/2016 - 03/30/2018 8 / 153 (b)   8 / 31 (f) 08/23/2011 Complete
FY 20 DSRA2   02/24/2020 - 08/09/2021 8 / 78 (b)   5 / 19 (f) 08/05/2014 Complete
FY 20 DSRA2   02/24/2020 - 08/09/2021 3 / 60 (b)   3 / 15 (f) 08/23/2011 Complete
FY 25 SRA4-1   07/28/2025 - 12/12/2026 2 / 84 (b)   3 / 31 (f) 02/06/2024 Active
  FY 25 SRA4-1   07/28/2025 - 12/12/2026 0 / 0 (b)   4 / 20 (f) 08/23/2011 Active
FY 29 SRA4-2   02/05/2029 - 02/04/2030 1 / 21 (b)   0 / 0 (f) 08/05/2014 Active
FY 29 SRA4-2   02/05/2029 - 02/04/2030 6 / 101 (b)   0 / 0 (f) 11/03/2020 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
HARPERS FERRY (LSD 49) 21852-254B
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: SDGO PLANNING YARD: PSNSY
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3795
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 11 EDPMA
SURVEY DATES: 07/13/2011 - 12/03/2012
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 25 SRA4-1
INSTALL DATES: 07/28/2025 - 12/12/2026
INSTALL LOCATION: SDGO
SHIPYARD: NASSCO
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 4 / 90 0 / 0 7 / 123 0 / 0 11 / 213
SANITARY SPACE / FIXTURES: 7 / 26 0 / 0 4 / 20 0 / 0 11 / 46
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 0 / 0 0 / 0 0 / 0 0 / 0 0 / 0
SANITARY SPACE / FIXTURES: 0 / 0 0 / 0 4 / 20 0 / 0 4 / 20
OTHER PROJECT:
PROJECT NO(S): BENL-E1293, HENL-E1326, BTRM-E1325, HTRP-E1327
REMARKS:
OTHER PROJ: INSTALL WITH 21852-254A
REMARKS: ORIGINAL REV A DRAWING PROVIDED WITHOUT BENFIT OF DESIGN VALIDATION OF PREVIOUS FY 17 PMA3-2 INSTALL. REVISED PROCUREMENT INFO PACKAGE FOR PROJECT BELOW POSTED 4/22/2024.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-SANITARY 14-LSD 49-03  A 644 - 8486047  REV A
VENTILATION-SANITARY 14-LSD 49-12  A1 510 - 8486048  REV A1
PIPE-SANITARY 14-LSD 49-20  A1 505 - 8486049  REV A1
ELECTRICAL-SANITARY 14-LSD 49-32  A1 331 - 8486050  REV A1
PROJECT NUMBERS(s) AND COMPARTMENTS
HTRP-S1327
02-26-0-L (16)
02-26-2-Q (0)
02-27-2-Q (1)
02-28-2-L (3)
 PT 4 (20)
MILESTONES SCHEDULED ACTUAL EVENTS
09/28/2023 08/23/2011 08/23/2011 START SURVEY
10/27/2023 09/03/2011 09/03/2011 COMPLETE SURVEY
11/28/2023 10/21/2011 10/20/2011 SEND SURVEY REPORT TO PM
04/04/2024 03/28/2013 05/30/2013 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
05/03/2024 04/28/2013 06/12/2013 SHIP RESPOND TO ADVANCE PLANNING NOTICE
06/03/2024 09/27/2013 10/08/2013 SO SUBMIT DRAWINGS TO PM & PY
06/03/2024 09/27/2013 10/10/2013 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
07/28/2025 07/28/2025 Pending START AVAILABILITY
07/28/2025 07/28/2025 Pending START PROJECT
12/12/2026 12/12/2026 Pending COMPLETE PROJECT
12/12/2026 12/12/2026 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 04/22/2024