Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, October 11, 2024 at 1:58 PM

Select by Ship Name: 

Select by Ship Hull: 

 

BENFOLD (DDG 65)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 11 EDSRA7   02/02/2011 - 09/09/2011 4 / 78 (b)   0 / 0 (f) 11/07/2007 Complete
FY 17 SRA4-1   10/19/2016 - 08/02/2017 4 / 27 (b)   5 / 17 (f) 06/21/2011 Complete
FY 19 DSRA4   04/10/2019 - 06/15/2020 1 / 75 (b)   6 / 28 (f) 06/21/2011 Complete
  FY 24 SRA5-1   10/10/2023 - 05/20/2024 2 / 132 (b)   8 / 27 (f) 09/11/2019 Complete
FY 26 SRA5-2   07/07/2026 - 03/01/2027 5 / 78 (b)   4 / 12 (f) 09/11/2019 Active
FY 30 DSRA5   06/03/2030 - 05/15/2031 16 / 39 (b)   8 / 25 (f) 09/11/2019 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
BENFOLD (DDG 65) 21940-241
PROJECT COMPLETED
TYCOM: SURFPAC HOMEPORT: SDGO PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3795
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 19 DSRA4
SURVEY DATES: 04/10/2019 - 06/15/2020
SURVEY LOCATION: SRFYOKO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 24 SRA5-1
INSTALL DATES: 10/10/2023 - 05/20/2024
INSTALL LOCATION: SRFYOKO
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 7 / 210 0 / 0 0 / 0 16 / 39 23 / 249
SANITARY SPACE / FIXTURES: 16 / 53 0 / 0 0 / 0 8 / 25 24 / 78
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 132 0 / 0 0 / 0 0 / 0 2 / 132
SANITARY SPACE / FIXTURES: 8 / 27 0 / 0 0 / 0 0 / 0 8 / 27
OTHER PROJECT:
PROJECT NO(S): BENL-E9409, BOFF-E9411, HENL-E9410, HOFF-E9412
REMARKS:
OTHER PROJ:
REMARKS:
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 13-DDG 65-01  C 640 - 8486028  REV C
ARRANGEMENT-SANITARY 13-DDG 65-03  C 644 - 8486031  REV C
VENTILATION-BERTHING 13-DDG 65-10  C 512 - 8486029  REV C
VENTILATION-SANITARY 13-DDG 65-12  C 512 - 8486032  REV C
PIPE-SANITARY 13-DDG 65-20  C 505 - 8486033  REV C
ELECTRICAL-BERTHING 13-DDG 65-30  C 331 - 8486030  REV C
ELECTRICAL-SANITARY 13-DDG 65-32  C 331 - 8486034  REV C
VENTILATION-MFG DET 13-DDG 65-52  C 512 - 8486035  REV C
REV C ISSUED 10/14/2022 FOR BENL-S9409 & HENL-S9410
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S9409
2-300-01-L (90)
3-97-02-L (42)
 PT 2 (132)
HENL-S9410
2-321-0-L (7)
2-326-0-L (4)
2-326-1-A (1)
2-326-2-A (1)
2-329-1-L (2)
2-335-1-L (2)
3-97-01-L (9)
3-102-1-A (1)
 PT 8 (27)
MILESTONES SCHEDULED ACTUAL EVENTS
12/10/2021 09/11/2019 09/11/2019 START SURVEY
01/07/2022 09/26/2019 09/26/2019 COMPLETE SURVEY
02/09/2022 10/25/2019 10/25/2019 SEND SURVEY REPORT TO PM
06/17/2022 07/15/2022 06/29/2022 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
07/15/2022 08/16/2022 07/06/2022 SHIP RESPOND TO ADVANCE PLANNING NOTICE
08/16/2022 10/14/2022 10/14/2022 SO SUBMIT DRAWINGS TO PM & PY
08/16/2022 10/14/2022 10/17/2022 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
04/13/2023 04/13/2023 Pending PROJECT MATERIAL PROCUREMENT FUNDED
07/11/2023 07/11/2023 Pending PROJECT INSTALLATION FUNDED
10/10/2023 10/10/2023 10/10/2023 START AVAILABILITY
10/10/2023 10/10/2023 10/10/2023 START PROJECT
05/20/2024 05/20/2024 05/20/2024 COMPLETE PROJECT
05/20/2024 05/20/2024 05/20/2024 COMPLETE AVAILABILITY
Project Record Last Updated: 05/20/2024