Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Friday, October 11, 2024 at 1:58 PM

Select by Ship Name: 

Select by Ship Hull: 

 

MILIUS (DDG 69)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 11 SRA6   02/08/2011 - 04/12/2011 1 / 96 (b)   3 / 20 (f) 01/13/1999 Complete
FY 13 EDSRA   12/17/2012 - 12/16/2013 5 / 78 (b)   8 / 25 (f) 03/07/2011 Complete
FY 16 ESRA   10/16/2015 - 12/15/2016 1 / 78 (b)   2 / 15 (f) 03/07/2011 Complete
FY 20 SRA4-2   03/12/2020 - 04/09/2021 1 / 42 (b)   2 / 10 (f) 03/07/2011 Complete
  FY 23 DSRA4   06/23/2023 - 05/15/2024 1 / 96 (b)   1 / 4 (f) 01/12/2016 Complete
FY 27 SRA5-1   04/19/2027 - 11/29/2027 4 / 27 (b)   5 / 17 (f) 01/12/2016 Active
FY 27 SRA5-1   04/19/2027 - 11/29/2027 16 / 38 (b)   9 / 29 (f) 02/14/2024 Active
FY 29 SRA5-2   06/25/2029 - 02/17/2030 5 / 78 (b)   8 / 25 (f) 04/19/2027 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
MILIUS (DDG 69) 21943-233
PROJECT COMPLETED
TYCOM: SURFPAC HOMEPORT: YOKO PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3795
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 16 ESRA
SURVEY DATES: 10/16/2015 - 12/15/2016
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 23 DSRA4
INSTALL DATES: 06/23/2023 - 05/15/2024
INSTALL LOCATION: SRFYOKO
SHIPYARD: TGD
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 1 / 96 4 / 27 0 / 0 0 / 0 5 / 123
SANITARY SPACE / FIXTURES: 3 / 20 5 / 17 0 / 0 0 / 0 8 / 37
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 1 / 96 0 / 0 0 / 0 0 / 0 1 / 96
SANITARY SPACE / FIXTURES: 1 / 4 0 / 0 0 / 0 0 / 0 1 / 4
OTHER PROJECT:
PROJECT NO(S): BCPO-E0314, HCPO-E0316, BENL-E6361, HENL-E6362
REMARKS:
OTHER PROJ:
REMARKS: Ship has requested Crew 3 berthing and shower area only in Crew 3 head 2-321-2-L, instead of CPO spaces.
BCPO & HCPO projects deferred to FY 27 and will retain Rev D for drawings.
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 12-DDG 69-01  E 640 - 8486036  REV E
ARRANGEMENT-SANITARY 12-DDG 69-03  E 644 - 8486039  REV E
VENTILATION-BERTHING 12-DDG 69-10  E 512 - 8486037  REV E
VENTILATION-SANITARY 12-DDG 69-12  E 512 - 8486040  REV E
PIPE-SANITARY 12-DDG 69-20  E 505 - 8486041  REV E
ELECTRICAL-BERTHING 12-DDG 69-30  E 331 - 8486038  REV E
ELECTRICAL-SANITARY 12-DDG 69-32  E 331 - 8486042  REV E
VENTILATION-MFG DET 12-DDG 69-52  E 512 - 8486043  REV E
BCPO & HCPO WILL RETAIN REV D.
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S6361
2-300-01-L (96)
 PT 1 (96)
HENL-S6362
2-321-2-L (SH AREA ONLY) (4)
 PT 1 (4)
MILESTONES SCHEDULED ACTUAL EVENTS
08/23/2021 01/12/2016 01/12/2016 START SURVEY
09/22/2021 01/18/2016 01/19/2016 COMPLETE SURVEY
10/22/2021 02/18/2016 02/12/2016 SEND SURVEY REPORT TO PM
02/28/2022 03/29/2022 03/14/2022 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
03/30/2022 04/28/2022 05/19/2022 SHIP RESPOND TO ADVANCE PLANNING NOTICE
04/29/2022 06/27/2022 05/18/2022 SO SUBMIT DRAWINGS TO PM & PY
04/29/2022 06/27/2022 05/18/2022 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
06/23/2023 06/23/2023 06/23/2023 START AVAILABILITY
06/23/2023 06/23/2023 06/23/2023 START PROJECT
05/15/2024 05/15/2024 05/15/2024 COMPLETE PROJECT
05/15/2024 05/15/2024 05/15/2024 COMPLETE AVAILABILITY
Project Record Last Updated: 05/20/2024