S H I P H A B I T A B I L I T Y P R O J E C T D A T A
DECATUR (DDG 73) |
21947-242
ACTIVE PROJECT
|
TYCOM: SURFPAC |
HOMEPORT: SDGO |
PLANNING YARD: BATH |
|
POC: Steve Ferderer, CNSP N43 |
PHONE: 619-437-3761 |
|
ENGINEERING WORK SCOPE |
SURVEY AVAILABILITY: |
FY 20 EDSRA |
SURVEY DATES: |
10/01/2019 - 10/26/2021 |
SURVEY LOCATION: |
SDGO |
DESIGN AGENT: |
DELPHINUS |
|
INSTALLATION WORK SCOPE |
INSTALL AVAILABILITY: |
FY 24 SRA3-1 |
INSTALL DATES: |
03/04/2024 - 01/10/2025 |
INSTALL LOCATION: |
PEARL |
SHIPYARD: |
|
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
4 / 81 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 81 |
SANITARY SPACE / FIXTURES: |
8 / 25 |
0 / 0 |
0 / 0 |
0 / 0 |
8 / 25 |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
4 / 81 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 81 |
SANITARY SPACE / FIXTURES: |
8 / 25 |
0 / 0 |
0 / 0 |
0 / 0 |
8 / 25 |
|
OTHER PROJECT: |
|
PROJECT NO(S): |
BENL-E9396, HENL-E9397 |
REMARKS: |
PICK UP REMAINING COMPARTMENTS |
|
OTHER PROJ: |
|
REMARKS: |
CREW COMPLEX 4, 5, 6 & 7
PROPOSED SKED CHG ) FY24 SRA3-1 SSD 04MAR24-10JAN25 (313) VICE 29JAN24-16SEP24 (232)
|
|
HABITABILITY DRAWING NUMBERS |
DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
ARRANGEMENT-BERTHING |
14-DDG 73-01 D |
640 - 8486052 REV D |
ARRANGEMENT-SANITARY |
14-DDG 73-03 D |
644 - 8486055 REV D |
VENTILATION-BERTHING |
14-DDG 73-10 D |
512 - 8486053 REV D |
VENTILATION-SANITARY |
14-DDG 73-12 D |
512 - 8486056 REV D |
PIPE-SANITARY |
14-DDG 73-20 D |
505 - 8486057 REV D |
ELECTRICAL-BERTHING |
14-DDG 73-30 D |
331 - 8486054 REV D |
ELECTRICAL-SANITARY |
14-DDG 73-32 D |
331 - 8486058 REV D |
VENTILATION-MFG DET |
14-DDG 73-52 D |
512 - 8486059 REV D |
|
PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S9396
3-300-1-L (24)
3-310-2-L (21)
3-338-1-L (18)
3-338-2-L (18)
PT 4 (81)
HENL-S9397
3-300-2-L (5)
3-306-2-A (1)
3-325-1-L (6)
3-335-1-A (1)
3-338-3-A (1)
3-338-4-A (1)
3-338-5-L (5)
3-338-6-L (5)
PT 8 (25)
|
|
MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
05/05/2022 |
03/03/2020 |
03/03/2020
|
START SURVEY |
06/03/2022 |
03/14/2020 |
03/18/2020
|
COMPLETE SURVEY |
07/05/2022 |
04/14/2020 |
03/31/2020
|
SEND SURVEY REPORT TO PM |
11/10/2022 |
11/04/2022 |
10/07/2022
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
12/09/2022 |
01/09/2023 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
01/09/2023 |
02/03/2023 |
02/10/2023
|
SO SUBMIT DRAWINGS TO PM & PY |
01/09/2023 |
02/03/2023 |
02/13/2023
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
09/06/2023 |
09/06/2023 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
12/04/2023 |
12/04/2023 |
Pending
|
PROJECT INSTALLATION FUNDED |
03/04/2024 |
03/04/2024 |
Pending
|
START AVAILABILITY |
03/04/2024 |
03/04/2024 |
Pending
|
START PROJECT |
01/10/2025 |
01/10/2025 |
Pending
|
COMPLETE PROJECT |
01/10/2025 |
01/10/2025 |
Pending
|
COMPLETE AVAILABILITY |
Project Record Last Updated: 06/09/2023 |
|