S H I P H A B I T A B I L I T Y P R O J E C T D A T A
HOWARD (DDG 83) |
22999-253A
ACTIVE PROJECT
|
TYCOM: SURFPAC |
HOMEPORT: YOKO |
PLANNING YARD: BATH |
|
POC: Steve Ferderer, CNSP N43 |
PHONE: 619-437-3761 |
|
ENGINEERING WORK SCOPE |
SURVEY AVAILABILITY: |
FY 18 DMP |
SURVEY DATES: |
02/26/2018 - 09/30/2019 |
SURVEY LOCATION: |
SDGO |
DESIGN AGENT: |
DELPHINUS |
|
INSTALLATION WORK SCOPE |
INSTALL AVAILABILITY: |
FY 25 SRA3-2 |
INSTALL DATES: |
04/07/2025 - 11/17/2025 |
INSTALL LOCATION: |
SRFYOKO |
SHIPYARD: |
TBD |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
1 / 87 |
5 / 27 |
0 / 0 |
17 / 40 |
23 / 154 |
SANITARY SPACE / FIXTURES: |
2 / 15 |
5 / 17 |
0 / 0 |
9 / 30 |
16 / 62 |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
0 / 0 |
5 / 27 |
0 / 0 |
0 / 0 |
5 / 27 |
SANITARY SPACE / FIXTURES: |
0 / 0 |
5 / 17 |
0 / 0 |
0 / 0 |
5 / 17 |
|
OTHER PROJECT: |
|
PROJECT NO(S): |
BCPO-E8340, BENL-E8341, BOFF-E8344, HCPO-E8342, HENL-E8343, HOFF-E8345 |
REMARKS: |
|
|
OTHER PROJ: |
INSTALL WITH 22999-252B |
REMARKS: |
|
|
HABITABILITY DRAWING NUMBERS |
DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
ARRANGEMENT-BERTHING |
14-DDG 83-01 D |
640 - 8565761 REV D |
ARRANGEMENT-SANITARY |
14-DDG 83-03 D |
644 - 8565764 REV D |
VENTILATION-BERTHING |
14-DDG 83-10 D |
512 - 8565762 REV D |
VENTILATION-SANITARY |
14-DDG 83-12 D |
512 - 8565765 REV D |
PIPE-SANITARY |
14-DDG 83-20 D |
505 - 8565766 REV D |
ELECTRICAL-BERTHING |
14-DDG 83-30 D |
331 - 8565763 REV D |
ELECTRICAL-SANITARY |
14-DDG 83-32 D |
331 - 8565767 REV D |
VENTILATION-MFG DET |
14-DDG 83-52 D |
512 - 8565779 REV D |
|
PROJECT NUMBERS(s) AND COMPARTMENTS |
BCPO-S8340
1-78-01-L (0)
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
PT 5 (27)
HCPO-S8342
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
PT 5 (17)
|
|
MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
06/08/2023 |
01/08/2019 |
01/08/2019
|
START SURVEY |
07/07/2023 |
01/17/2019 |
01/17/2019
|
COMPLETE SURVEY |
08/08/2023 |
02/15/2019 |
02/15/2019
|
SEND SURVEY REPORT TO PM |
12/14/2023 |
12/14/2023 |
Pending
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
01/12/2024 |
01/12/2024 |
Pending
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
02/12/2024 |
02/12/2024 |
Pending
|
SO SUBMIT DRAWINGS TO PM & PY |
02/12/2024 |
02/12/2024 |
Pending
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
10/09/2024 |
10/09/2024 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
01/06/2025 |
01/06/2025 |
Pending
|
PROJECT INSTALLATION FUNDED |
04/07/2025 |
04/07/2025 |
Pending
|
START AVAILABILITY |
04/07/2025 |
04/07/2025 |
Pending
|
START PROJECT |
11/17/2025 |
11/17/2025 |
Pending
|
COMPLETE PROJECT |
11/17/2025 |
11/17/2025 |
Pending
|
COMPLETE AVAILABILITY |
Project Record Last Updated: 06/19/2023 |
|