Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, June 11, 2024 at 8:57 AM

Select by Ship Name: 

Select by Ship Hull: 

 

KIDD (DDG 100)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 22 SRA2-2   11/19/2021 - 06/10/2022 6 / 84 (b)   8 / 25 (f) 07/14/2015 Complete
  FY 25 DMP   01/06/2025 - 02/24/2027 6 / 207 (b)   10 / 52 (f) 07/14/2015 Active
FY 30 SRA3-1   05/13/2030 - 12/23/2030 17 / 34 (b)   13 / 30 (f) 02/18/2025 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
KIDD (DDG 100) 23152-252
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: EVERETT PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3761
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 15 DSRA1
SURVEY DATES: 07/09/2015 - 04/30/2016
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 25 DMP
INSTALL DATES: 01/06/2025 - 02/24/2027
INSTALL LOCATION: EVER
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 9 / 312 4 / 27 0 / 0 0 / 0 13 / 339
SANITARY SPACE / FIXTURES: 15 / 70 5 / 17 0 / 0 0 / 0 20 / 87
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 180 4 / 27 0 / 0 0 / 0 6 / 207
SANITARY SPACE / FIXTURES: 5 / 35 5 / 17 0 / 0 0 / 0 10 / 52
OTHER PROJECT:
PROJECT NO(S): BCPO-E5351, BENL-E5352, HCPO-E5353 & HENL-E5354
REMARKS: REV B DRWAINGS ISSUED 12/08/2023. DRAWINGS RE-ISSUED AS REV C WITHOUT CREW SANITARY SPACE 3-97-01-L.
OTHER PROJ:
REMARKS: CPO COMPLEX #1 & #2, CREW COMPLEX #1, #2 & #3.
CREW BERTHING 3-97-02-L AND CREW SANITARY 3-97-01-L REMOVED FROM FY 25 WORK SCOPE. SA 86821 SCHEDULED FOR THIS AVAIL
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 15-DDG 100-01  C 640 - 8718335  REV C
ARRANGEMENT-SANITARY 15-DDG 100-03  C 644 - 8718338  REV C
VENTILATION-BERTHING 15-DDG 100-10  C 512 - 8718336  REV C
VENTILATION-SANITARY 15-DDG 100-12  C 512 - 8718339  REV C
PIPE-SANITARY 15-DDG 100-20  C 505 - 8718340  REV C
ELECTRICAL-BERTHING 15-DDG 100-30  C 331 - 8718337  REV C
ELECTRICAL-SANITARY 15-DDG 100-32  C 331 - 8718341  REV C
VENTILATION-MFG DET 15-DDG 100-52  C 512 - 8718342  REV C
DRAWINGS RE-ISSUED AS REV C WITHOUT CREW SANITARY SPACE 3-97-01-L.
PROJECT NUMBERS(s) AND COMPARTMENTS
BCPO-S5351
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
 PT 4 (27)
BENL-S4405
2-78-01-L (87)
2-300-01-L (93)
 PT 2 (180)
HCPO-S5353
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
 PT 5 (17)
HENL-S4407
2-97-01-L (14)
2-102-1-A (1)
2-321-2-L (10)
2-326-0-L (9)
2-326-2-A (1)
 PT 5 (35)
MILESTONES SCHEDULED ACTUAL EVENTS
03/09/2023 07/14/2015 07/14/2015 START SURVEY
04/07/2023 07/25/2015 07/25/2015 COMPLETE SURVEY
05/09/2023 08/25/2015 08/21/2015 SEND SURVEY REPORT TO PM
09/14/2023 09/14/2023 09/14/2023 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
10/13/2023 10/13/2023 09/18/2023 SHIP RESPOND TO ADVANCE PLANNING NOTICE
11/13/2023 02/16/2024 04/01/2024 SO SUBMIT DRAWINGS TO PM & PY
11/13/2023 02/16/2024 04/01/2024 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
07/10/2024 07/10/2024 Pending PROJECT MATERIAL PROCUREMENT FUNDED
10/07/2024 10/07/2024 Pending PROJECT INSTALLATION FUNDED
01/06/2025 01/06/2025 Pending START AVAILABILITY
01/06/2025 01/06/2025 Pending START PROJECT
02/24/2027 02/24/2027 Pending COMPLETE PROJECT
02/24/2027 02/24/2027 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 04/01/2024