Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, November 28, 2023 at 7:12 AM

Select by Ship Name: 

Select by Ship Hull: 

 

HALSEY (DDG 97)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 16 DSRA1   11/09/2015 - 10/05/2016 3 / 42 (b)   8 / 38 (f) NA Complete
FY 22 SRA2-2   01/17/2022 - 12/08/2022 1 / 93 (b)   3 / 20 (f) 04/03/2013 Complete
FY 22 SRA2-2   01/17/2022 - 12/08/2022 3 / 36 (b)   4 / 12 (f) 07/11/2017 Complete
FY 22 SRA2-2   01/17/2022 - 12/08/2022 3 / 45 (b)   4 / 13 (f) NA Complete
FY 24 DMP1   09/23/2024 - 11/11/2026 1 / 87 (b)   2 / 15 (f) 04/03/2013 Active
  FY 24 DMP1   09/23/2024 - 11/11/2026 5 / 75 (b)   7 / 27 (f) 03/01/2022 Active
FY 28 DMP2   09/25/2028 - 11/28/2030 17 / 36 (b)   11 / 31 (f) 10/01/2024 Active
FY 32 SRA3-1   09/06/2032 - 04/17/2033 1 / 93 (b)   3 / 20 (f) 04/03/2013 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
HALSEY (DDG 97) 23154-244B
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: SDGO PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3761
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 22 SRA2-2
SURVEY DATES: 01/17/2022 - 12/08/2022
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 24 DMP1
INSTALL DATES: 09/23/2024 - 11/11/2026
INSTALL LOCATION: SDGO
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 1 / 48 4 / 27 0 / 0 0 / 0 5 / 75
SANITARY SPACE / FIXTURES: 2 / 10 5 / 17 0 / 0 0 / 0 7 / 27
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 1 / 48 4 / 27 0 / 0 0 / 0 5 / 75
SANITARY SPACE / FIXTURES: 2 / 10 5 / 17 0 / 0 0 / 0 7 / 27
OTHER PROJECT:
PROJECT NO(S): BCPO-E8290, BENL-E4462, HCPO-E8313, HENL-E4463
REMARKS:
OTHER PROJ:
REMARKS: CPO AND CREW COMPLEX #2
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 15-DDG 97-01  C 640 - 8565827  REV C
ARRANGEMENT-SANITARY 15-DDG 97-03  C 644 - 8565830  REV C
VENTILATION-BERTHING 15-DDG 97-10  C 512 - 8565828  REV C
VENTILATION-SANITARY 15-DDG 97-12  C 512 - 8565831  REV C
PIPE-SANITARY 15-DDG 97-20  C 505 - 8565832  REV C
ELECTRICAL-BERTHING 15-DDG 97-30  C 331 - 8565829  REV C
ELECTRICAL-SANITARY 15-DDG 97-32  C 331 - 8565833  REV C
VENTILATION-MFG DET 15-DDG 97-52  C 512 - 8565834  REV C
PROJECT NUMBERS(s) AND COMPARTMENTS
BCPO-S8290
1-110-0-L (12)
1-110-1-L (3)
1-115-1-L (3)
2-347-1-L (9)
 PT 4 (27)
BENL-S4462
3-97-02-L (48)
 PT 1 (48)
HCPO-S8313
1-110-2-L (7)
1-115-2-A (1)
1-120-1-L (3)
2-338-3-L (5)
2-344-1-A (1)
 PT 5 (17)
HENL-S4463
3-97-01-L (9)
3-102-1-A (1)
 PT 2 (10)
MILESTONES SCHEDULED ACTUAL EVENTS
11/23/2022 03/01/2022 03/01/2022 START SURVEY
12/23/2022 03/15/2022 03/15/2022 COMPLETE SURVEY
01/24/2023 04/22/2022 04/05/2022 SEND SURVEY REPORT TO PM
06/01/2023 06/01/2023 06/30/2023 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
06/30/2023 06/30/2023 07/18/2023 SHIP RESPOND TO ADVANCE PLANNING NOTICE
07/31/2023 08/14/2023 08/14/2023 SO SUBMIT DRAWINGS TO PM & PY
07/31/2023 08/14/2023 08/15/2023 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
03/27/2024 03/27/2024 Pending PROJECT MATERIAL PROCUREMENT FUNDED
06/24/2024 06/24/2024 Pending PROJECT INSTALLATION FUNDED
09/23/2024 09/23/2024 Pending START AVAILABILITY
09/23/2024 09/23/2024 Pending START PROJECT
11/11/2026 11/11/2026 Pending COMPLETE PROJECT
11/11/2026 11/11/2026 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 08/15/2023