Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, November 28, 2023 at 7:12 AM

Select by Ship Name: 

Select by Ship Hull: 

 

SAMPSON (DDG 102)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 18 DSRA1   07/16/2018 - 04/12/2019 5 / 66 (b)   8 / 25 (f) 08/13/2015 Complete
  FY 23 SRA2-1   03/21/2023 - 11/17/2023 2 / 135 (b)   4 / 25 (f) 08/13/2015 Complete
FY 27 DMP   02/08/2027 - 03/28/2029 6 / 120 (b)   8 / 37 (f) 08/13/2015 Active
FY 27 DMP   02/08/2027 - 03/28/2029 17 / 40 (b)   11 / 32 (f) 03/21/2023 Active
FY 32 SRA3-1   12/16/2031 - 07/27/2032 6 / 84 (b)   8 / 25 (f) 08/13/2015 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
SAMPSON (DDG 102) 23161-232
PROJECT COMPLETED
TYCOM: SURFPAC HOMEPORT: EVERETT PLANNING YARD: BATH
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3761
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 15 SRA1-3
SURVEY DATES: 07/21/2015 - 01/28/2016
SURVEY LOCATION: SDGO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 23 SRA2-1
INSTALL DATES: 03/21/2023 - 11/17/2023
INSTALL LOCATION: EVER
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 7 / 321 4 / 27 0 / 0 0 / 0 11 / 348
SANITARY SPACE / FIXTURES: 15 / 68 5 / 17 0 / 0 0 / 0 20 / 85
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 2 / 135 0 / 0 0 / 0 0 / 0 2 / 135
SANITARY SPACE / FIXTURES: 4 / 25 0 / 0 0 / 0 0 / 0 4 / 25
OTHER PROJECT:
PROJECT NO(S): BCPO-E5355, BENL-E5356, HCPO-E5357 & HENL-E5358
REMARKS:
OTHER PROJ:
REMARKS: CRW COMPLEX #1 & #2
PROPOSED AVAIL EXTENSION TO 10/29/23
HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 15-DDG 102-01  B 640 - 8718343  REV B
ARRANGEMENT-SANITARY 15-DDG 102-03  B 644 - 8718346  REV B
VENTILATION-BERTHING 15-DDG 102-10  B 512 - 8718344  REV B
VENTILATION-SANITARY 15-DDG 102-12  B 512 - 8718347  REV B
PIPE-SANITARY 15-DDG 102-20  B 505 - 8718348  REV B
ELECTRICAL-BERTHING 15-DDG 102-30  B 331 - 8718345  REV B
ELECTRICAL-SANITARY 15-DDG 102-32  B 331 - 8718349  REV B
VENTILATION-MFG DET 15-DDG 102-52  B 512 - 8718350  REV B
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S0444
2-78-01-L (87)
3-97-02-L (48)
 PT 2 (135)
HENL-S0445
2-97-01-L (14)
2-102-1-A (1)
3-97-01-L (9)
3-102-1-A (1)
 PT 4 (25)
MILESTONES SCHEDULED ACTUAL EVENTS
05/21/2021 08/13/2015 08/13/2015 START SURVEY
06/18/2021 08/26/2015 08/26/2015 COMPLETE SURVEY
07/21/2021 09/25/2015 09/25/2015 SEND SURVEY REPORT TO PM
11/26/2021 02/14/2020 02/13/2020 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
12/23/2021 03/16/2020 02/18/2020 SHIP RESPOND TO ADVANCE PLANNING NOTICE
01/25/2022 10/22/2021 10/22/2021 SO SUBMIT DRAWINGS TO PM & PY
01/25/2022 10/22/2021 10/22/2021 SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
03/21/2023 03/21/2023 03/21/2023 START AVAILABILITY
03/21/2023 03/21/2023 03/21/2023 START PROJECT
11/17/2023 11/17/2023 11/17/2023 COMPLETE PROJECT
11/17/2023 11/17/2023 11/17/2023 COMPLETE AVAILABILITY
Project Record Last Updated: 11/15/2023