S H I P H A B I T A B I L I T Y P R O J E C T D A T A
MAKIN ISLAND (LHD 8) |
23171-234
ACTIVE PROJECT
|
TYCOM: SURFPAC |
HOMEPORT: SDGO |
PLANNING YARD: NNSY |
|
POC: Steve Ferderer, CNSP N43 |
PHONE: 619-437-3795 |
|
ENGINEERING WORK SCOPE |
SURVEY AVAILABILITY: |
FY 17 DPMA1 |
SURVEY DATES: |
07/31/2017 - 09/06/2019 |
SURVEY LOCATION: |
SDGO |
DESIGN AGENT: |
DELPHINUS |
|
INSTALLATION WORK SCOPE |
INSTALL AVAILABILITY: |
FY 23 SRA2-2 |
INSTALL DATES: |
08/21/2023 - 12/19/2024 |
INSTALL LOCATION: |
SDGO |
SHIPYARD: |
|
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
4 / 294 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 294 |
SANITARY SPACE / FIXTURES: |
12 / 65 |
0 / 0 |
0 / 0 |
0 / 0 |
12 / 65 |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
4 / 294 |
0 / 0 |
0 / 0 |
0 / 0 |
4 / 294 |
SANITARY SPACE / FIXTURES: |
12 / 65 |
0 / 0 |
0 / 0 |
0 / 0 |
12 / 65 |
|
OTHER PROJECT: |
|
PROJECT NO(S): |
|
REMARKS: |
|
|
OTHER PROJ: |
|
REMARKS: |
PROJECT RESCHEDULED BACK TO FY 23. PROCUREMENT INFO PKG RE-RAN FOR PRICING UPDATE 4/11/22. |
|
HABITABILITY DRAWING NUMBERS |
DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
ARRANGEMENT-BERTHING |
18-LHD 8-01 - |
640 - 8788854 REV - |
ARRANGEMENT-SANITARY |
18-LHD 8-03 - |
644 - 8788857 REV - |
VENTILATION-BERTHING |
18-LHD 8-10 - |
512 - 8788855 REV - |
VENTILATION-SANITARY |
18-LHD 8-12 - |
512 - 8788858 REV - |
PIPE-FLUSHING WATER |
18-LHD 8-26 - |
521 - 8788859 REV - |
PIPE-PLUMBING DRAIN |
18-LHD 8-27 - |
528 - 8788860 REV - |
PIPE - POTABLE |
18-LHD 8-28 - |
533 - 8788861 REV - |
ELECTRICAL-BERTHING |
18-LHD 8-30 - |
331 - 8788856 REV - |
ELECTRICAL-SANITARY |
18-LHD 8-32 - |
331 - 8788862 REV - |
ELECTRICAL-POWER SYSTEM |
18-LHD 8-39 - |
321 - 8788863 REV - |
VENTILATION-MFG DET |
18-LHD 8-52 - |
512 - 8788864 REV - |
|
PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S7362
1-25-0-L (93)
1-26-1-L (42)
1-26-2-L (51)
1-33-0-L (108)
PT 4 (294)
HENL-S7363
1-31-0-L (6)
1-31-1-A (1)
1-31.5-0-L (8)
1-31.5-1-L (9)
1-31.5-2-L (8)
1-31.5-3-L (7)
1-31.5-4-L (2)
1-32.5-3-L (2)
1-32.5-4-A (1)
1-38.5-0-L (15)
1-40-1-L (5)
1-40.5-1-A (1)
PT 12 (65)
|
|
MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
10/21/2021 |
07/10/2018 |
07/10/2018
|
START SURVEY |
11/19/2021 |
07/22/2018 |
07/22/2018
|
COMPLETE SURVEY |
12/21/2021 |
08/22/2018 |
08/21/2018
|
SEND SURVEY REPORT TO PM |
04/28/2022 |
05/01/2020 |
05/06/2020
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
05/27/2022 |
06/01/2020 |
05/06/2020
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
06/27/2022 |
07/31/2020 |
07/31/2020
|
SO SUBMIT DRAWINGS TO PM & PY |
06/27/2022 |
07/31/2020 |
08/03/2020
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
02/22/2023 |
02/22/2023 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
05/22/2023 |
05/22/2023 |
Pending
|
PROJECT INSTALLATION FUNDED |
08/21/2023 |
08/21/2023 |
08/21/2023
|
START AVAILABILITY |
08/21/2023 |
08/21/2023 |
08/21/2023
|
START PROJECT |
12/19/2024 |
12/19/2024 |
Pending
|
COMPLETE PROJECT |
12/19/2024 |
12/19/2024 |
Pending
|
COMPLETE AVAILABILITY |
Project Record Last Updated: 06/17/2024 |
|