S H I P H A B I T A B I L I T Y P R O J E C T D A T A
GREEN BAY (LPD 20) |
3012A-252
ACTIVE PROJECT
|
TYCOM: SURFPAC |
HOMEPORT: SASEBO |
PLANNING YARD: HII |
|
POC: Steve Ferderer, CNSP N43 |
PHONE: 619-437-3761 |
|
ENGINEERING WORK SCOPE |
SURVEY AVAILABILITY: |
FY 17 SRA2-2 |
SURVEY DATES: |
09/11/2017 - 02/28/2018 |
SURVEY LOCATION: |
SASBO |
DESIGN AGENT: |
DELPHINUS |
|
INSTALLATION WORK SCOPE |
INSTALL AVAILABILITY: |
FY 25 DSRA2 |
INSTALL DATES: |
02/10/2025 - 10/08/2026 |
INSTALL LOCATION: |
SDGO |
SHIPYARD: |
|
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
12 / 330 |
8 / 34 |
0 / 0 |
0 / 0 |
20 / 364 |
SANITARY SPACE / FIXTURES: |
21 / 88 |
8 / 15 |
0 / 0 |
0 / 0 |
29 / 103 |
|
ITEM |
CREW |
CPO |
TROOP |
OFFICER |
TOTAL |
LIVING SPACES / BERTHS: |
12 / 330 |
0 / 0 |
0 / 0 |
0 / 0 |
12 / 330 |
SANITARY SPACE / FIXTURES: |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
0 / 0 |
|
OTHER PROJECT: |
|
PROJECT NO(S): |
BCPO-E7267, BENL-E7268, HCPO-E7345, HENL-E7346 |
REMARKS: |
|
|
OTHER PROJ: |
|
REMARKS: |
LWMB WILL BE INSTALLED VICE SIT-UP BERTHS.
|
|
HABITABILITY DRAWING NUMBERS |
DISCIPLINE |
HAB DRAWING NUMBER |
NAVSEA DRAWING NUMBER |
ARRANGEMENT-BERTHING |
17-LPD 20-01 B |
640 - 8740887 REV B |
VENTILATION-BERTHING |
17-LPD 20-10 B |
512 - 8740888 REV B |
ELECTRICAL-BERTHING |
17-LPD 20-30 B |
331 - 8740889 REV B |
NO 52 DWG REQUIRED FOR THIS INSTALLATION REV A ISSUED, NOT INSTALLED. REWORK DRAWINGS FOR LWMB AND ISSUE AS REV B. |
|
PROJECT NUMBERS(s) AND COMPARTMENTS |
BENL-S4467
3-10-2-L (0)
3-33-0-L (39)
3-33-2-L (27)
3-37-0-L (42)
3-48-0-L (36)
3-53-0-L (39)
3-63-2-L (18)
3-84-1-L (12)
3-95-1-L (21)
3-100-2-L (15)
4-33-2-L (36)
4-80-1-L (45)
PT 12 (330)
|
|
MILESTONES |
SCHEDULED |
ACTUAL |
EVENTS |
04/13/2023 |
09/17/2017 |
09/17/2017
|
START SURVEY |
05/12/2023 |
10/05/2017 |
10/05/2017
|
COMPLETE SURVEY |
06/13/2023 |
11/03/2017 |
10/18/2017
|
SEND SURVEY REPORT TO PM |
10/19/2023 |
05/12/2023 |
05/03/2023
|
TC ISSUE ADVANCE PLANNING NOTICE TO SHIP |
11/17/2023 |
06/12/2023 |
05/07/2023
|
SHIP RESPOND TO ADVANCE PLANNING NOTICE |
12/18/2023 |
12/18/2023 |
Pending
|
SO SUBMIT DRAWINGS TO PM & PY |
12/18/2023 |
12/18/2023 |
Pending
|
SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM |
08/14/2024 |
08/14/2024 |
Pending
|
PROJECT MATERIAL PROCUREMENT FUNDED |
11/08/2024 |
11/08/2024 |
Pending
|
PROJECT INSTALLATION FUNDED |
02/10/2025 |
02/10/2025 |
Pending
|
START AVAILABILITY |
02/10/2025 |
02/10/2025 |
Pending
|
START PROJECT |
10/08/2026 |
10/08/2026 |
Pending
|
COMPLETE PROJECT |
10/08/2026 |
10/08/2026 |
Pending
|
COMPLETE AVAILABILITY |
Project Record Last Updated: 07/24/2023 |
|