Ship Project Status Report
(Blue Book)

Blue Book Last Updated: Tuesday, November 28, 2023 at 7:12 AM

Select by Ship Name: 

Select by Ship Hull: 

 

GREEN BAY (LPD 20)
PROJECT INSTALL AVAIL WORK SCOPE SURVEY STATUS
FY 20 SRA2-3   04/10/2020 - 09/08/2020 12 / 330 (b)   21 / 88 (f) 09/17/2017 Complete
  FY 25 DSRA2   02/10/2025 - 10/08/2026 12 / 330 (b)   0 / 0 (f) 09/17/2017 Active
FY 29 SRA3-1   04/16/2029 - 01/15/2030 6 / 225 (b)   12 / 57 (f) 05/26/2021 Active

 

S H I P    H A B I T A B I L I T Y    P R O J E C T    D A T A
GREEN BAY (LPD 20) 3012A-252
ACTIVE PROJECT
TYCOM: SURFPAC HOMEPORT: SASEBO PLANNING YARD: HII
POC: Steve Ferderer, CNSP N43 PHONE: 619-437-3761
ENGINEERING WORK SCOPE
SURVEY AVAILABILITY: FY 17 SRA2-2
SURVEY DATES: 09/11/2017 - 02/28/2018
SURVEY LOCATION: SASBO
DESIGN AGENT: DELPHINUS
INSTALLATION WORK SCOPE
INSTALL AVAILABILITY: FY 25 DSRA2
INSTALL DATES: 02/10/2025 - 10/08/2026
INSTALL LOCATION: SDGO
SHIPYARD:
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 12 / 330 8 / 34 0 / 0 0 / 0 20 / 364
SANITARY SPACE / FIXTURES: 21 / 88 8 / 15 0 / 0 0 / 0 29 / 103
ITEM CREW CPO TROOP OFFICER TOTAL
LIVING SPACES / BERTHS: 12 / 330 0 / 0 0 / 0 0 / 0 12 / 330
SANITARY SPACE / FIXTURES: 0 / 0 0 / 0 0 / 0 0 / 0 0 / 0
OTHER PROJECT:
PROJECT NO(S): BCPO-E7267, BENL-E7268, HCPO-E7345, HENL-E7346
REMARKS:
OTHER PROJ:
REMARKS: LWMB WILL BE INSTALLED VICE SIT-UP BERTHS.

HABITABILITY DRAWING NUMBERS
DISCIPLINE HAB DRAWING NUMBER NAVSEA DRAWING NUMBER
ARRANGEMENT-BERTHING 17-LPD 20-01  B 640 - 8740887  REV B
VENTILATION-BERTHING 17-LPD 20-10  B 512 - 8740888  REV B
ELECTRICAL-BERTHING 17-LPD 20-30  B 331 - 8740889  REV B
NO 52 DWG REQUIRED FOR THIS INSTALLATION
REV A ISSUED, NOT INSTALLED. REWORK DRAWINGS FOR LWMB AND ISSUE AS REV B.
PROJECT NUMBERS(s) AND COMPARTMENTS
BENL-S4467
3-10-2-L (0)
3-33-0-L (39)
3-33-2-L (27)
3-37-0-L (42)
3-48-0-L (36)
3-53-0-L (39)
3-63-2-L (18)
3-84-1-L (12)
3-95-1-L (21)
3-100-2-L (15)
4-33-2-L (36)
4-80-1-L (45)
 PT 12 (330)
MILESTONES SCHEDULED ACTUAL EVENTS
04/13/2023 09/17/2017 09/17/2017 START SURVEY
05/12/2023 10/05/2017 10/05/2017 COMPLETE SURVEY
06/13/2023 11/03/2017 10/18/2017 SEND SURVEY REPORT TO PM
10/19/2023 05/12/2023 05/03/2023 TC ISSUE ADVANCE PLANNING NOTICE TO SHIP
11/17/2023 06/12/2023 05/07/2023 SHIP RESPOND TO ADVANCE PLANNING NOTICE
12/18/2023 12/18/2023 Pending SO SUBMIT DRAWINGS TO PM & PY
12/18/2023 12/18/2023 Pending SO DELIVER PROCUREMENT INFORMATION PACKAGE TO PM
08/14/2024 08/14/2024 Pending PROJECT MATERIAL PROCUREMENT FUNDED
11/08/2024 11/08/2024 Pending PROJECT INSTALLATION FUNDED
02/10/2025 02/10/2025 Pending START AVAILABILITY
02/10/2025 02/10/2025 Pending START PROJECT
10/08/2026 10/08/2026 Pending COMPLETE PROJECT
10/08/2026 10/08/2026 Pending COMPLETE AVAILABILITY
Project Record Last Updated: 07/24/2023